AIURION / JOB RELEASE & CLOSEOUT
No CAD upload
Conditional

Release only after the named conditions are owned.

Planning may continue, but production should not begin until the conditions below are resolved.

Part
Control enclosure
Revision
Rev C
Quantity
24
Due
Aug 28, 2026
Material
6061-T6 aluminum
Operations
5
Edit inputs

Release conditions

4 open

04
  1. 01
    Assign available material

    The specified material is not assigned to this job.

    Block
  2. 02
    Assign the material lot

    The material is specified, but no available or ordered lot is attached.

    Block
  3. 03
    Name the first article owner

    The first article needs a named person responsible for acceptance.

    Own
  4. 04
    Confirm outside-process timing

    Outside work is planned, but its lead time has not been confirmed against the due date.

    Risk
See the complete example record or check your own job.The example is read-only and no data was submitted.